Tokyo International Airport

As efforts to strengthen the functions of airports in the Tokyo metropolitan area move forward in preparation for 2020, a project is underway to expand the southern area of Tokyo International Airport's Terminal 2 passenger terminal to accommodate international flights in anticipation of a further increase in the number of international passengers.
With a structure in which design and construction were separated, we acted as a technical advisor, supporting ordering and providing Cost Management services.

DATA

Year of completion2020
LocationOta Ward, Tokyo

Google map

Building usage Public, Culture and Sports
Site areaApproximately 943,000㎡
Total floor areaApproximately 67,000㎡
Scale4 floors above ground, 1 floor below ground
structureSteel
Our BusinessCM (Construction Management), Cost Consulting
CM ContentsProgram Management

Update : 2022.07.26

Tags